1. What a transfer actually changes
When a licence changes hands, the plant usually stays where it is. The new operator inherits equipment sized for the previous owner’s plan: their target product, their ore blend, their throughput.
The risk is not that the machines are worn. It is that they were sized for a different duty, and the mismatch only shows up after the first month of running.
2. Re-baseline before ordering anything new
Survey what is actually installed — model, drive power, deck area, tank volume — rather than what the handover documents say. Nameplate data and as-built data diverge more often than not.
Then test the ore. A licence transfer frequently comes with a change of mining plan, and a different bench or a different seam can shift clay content and liberation size enough to change the circuit.
3. Order of work
Survey, then sample, then test, then size. Buying the obvious missing machine first is the common mistake: it is usually the second bottleneck that turns out to matter.
Keep the existing units in the flow where they still do their job. Replacing a working roughing stage to match a new design is rarely the best use of the capital.