1. When the flow must be settled first

For a new plant on an ore you have not run before, the flow comes first. Feed size, clay content, liberation size and the target product decide how many stages you need, and no machine choice survives a wrong stage count.

Buying equipment before that is settled usually produces mismatched capacity: a roughing unit sized for a feed the crusher never delivers, or a cleaning stage that cannot keep up with the roughing concentrate.

2. What a flow design has to state

A usable flow states five things: the feed size distribution, the clay and slime content, the target concentrate and its required grade, the water balance, and the site layout constraints.

Without those five, any equipment list is a guess. With them, sizing each stage is arithmetic rather than opinion.

3. Where buying machines first is defensible

There is one case where it works: a brownfield expansion on ore the operator has run for years. The flow is already proven on site, and the only open question is capacity.

Even then, keep the new unit independent enough to be re-staged later. A machine that can only ever sit in one position in the circuit is a machine you will replace rather than move.